Besides having to deal with different gas quality standards from the many different utilities managing the pipelines across the US, the major challenge for RNG injection is the pipeline infrastructure. Even the most perfect project can be non-viable if the pipeline is not close enough for injection or cannot accept the volume you are producing (i.e. summer months). Transporting the gas is feasible but it eats up on your revenue and lowers the CI score.