Reply To: Potential failure modes in RNG project development

  • Peter

    Member
    2 March 2026 at 4:55 pm

    Not sure it they are the top three, but three I think are worth mentioning.

    1) Lack of RNG off-take certainty slowing FID

    2) Insufficient detail in initial design basis leads to change orders, and delays

    3) Regulatory delays related to environmental compliance, gas safety approvals, and pipeline interconnection